Town of
Brookfield
Municipal
Building Committee
Regular
Monthly Meeting
August 17,
2010 7:00 P.M.
Town Hall
Room 133
1. Call
to Order: Meeting was called to order
at 7:08 P.M. by Chairman Paul Checco.
Present: Committee
Members: George Brown, Jr. and Josh
Flowers. Also in attendance: Curt Verdi,
Verdi Construction (left at 7:34 P.M.); Mark Schweitzer, Morganti Group, Inc.
(left at 7:42 P.M.); and members of the public.
Absent: Anthony Licursi, John Martino,
Jr. and William Perrone.
2. Approval
of Minutes:
o April 21,
2009 Meeting - Approval of the
minutes from the April 21, 2009 meeting was tabled pending clarification from
the Town Attorney regarding wording for the reason for the Executive Session.
o July 20, 2010
Meeting A motion was made by Josh Flowers to approve the minutes from
the July 20, 2010 meeting. The motion
was seconded by George Brown, Jr. and passed, 3-0.
3. Senior
Center Update
a. Perkins
and Will Architects:
Jennifer Rodriguez was unable to attend the meeting.
b. Verdi
Construction:
Mr. Verdi provided an update on the project. He submitted an updated schedule dated
8/16/10. The masonry was recently
finished. Preparation for the finished
coat, stucco, aluminum storefront installation and drywall were completed last
week. Acoustical ceiling, painting and
tile were started. Flooring preparation
will begin next week. Fabricating
casework will be started any day.
Approved shop drawings have been received. Glazing portion of the storefront will be a
few weeks behind schedule. HVAC
equipment is expected to be delivered tomorrow and will be installed before the
end of the month. The electrical
contractor was onsite today. A LEED
required flushout is on the schedule for October 1st. Occupancy is anticipated for October 6th. Mr. Brown requested that the six black bricks
to the left of the entrance be removed and replaced. Chairman Checco reported that two of the
biggest delays were the sprinkler design system and the design for the
mechanical system. Also contributing to
the delay in the schedule was the ordering of the windows and the
cabinetry. Vice Chairman Flowers asked
about the sign-off for the mechanical system.
Mr. Verdi stated that they need to submit the asbuilt for the HVAC
system which is almost done. The asbuilt
for the duct work has been completed.
They need to asbuilt the final locations of the diffusers. Chairman Checco reported that yesterday a
revised proposal was received from the LEED Commission agent for $9,000.
The following Change Order Requests were submitted and
discussed:
Change Order Request #31, Revision #1 Data
Conduit/Boxes for Town I.T. Department At last months MBC meeting, a motion was made to return C.O.R. #31 in
the amount of $1,909.00 for a price review.
C.O.R. #31 was resubmitted. A motion was made by Josh Flowers to
approve Change Order Request #31, Revision #1 Data Conduit/Boxes for Town
I.T. Department dated 8/7/10 in the amount of $1,717.00. The motion was seconded by George Brown, Jr. and
passed unanimously, 3-0.
Change Order Request #6, Revision #1 Craft Room
Ceiling Changes - The sky lights
were removed from the proposal. At last
months meeting, a credit for $20,220 was approved which would offset this
C.O.R. A motion was made by George Brown, Jr. to approve Change Order Request
#6, Revision #1 Craft Room Ceiling Changes dated 8/7/10 in the amount of
$22,323.81. The motion was seconded by
Josh Flowers and passed unanimously, 3-0.
Change Order Request #29, Revision #1 Gypsum Board
Ceiling at Kiln Room A motion was made by George Brown, Jr. to
approve Change Order Request #29, Revision #1 Gypsum Board Ceiling at Kiln
Room dated 8/17/10 in the amount of $3,373.70.
The motion was seconded by Josh Flowers and passed unanimously, 3-0.
Verdi Application and Certification for Payment #11
was submitted The
requisition had not been signed by Jennifer Rodriguez. A
motion was made by George Brown, Jr. to approve Revised Application and
Certification for Payment #11 from Verdi Construction dated 8/16/10 in the
amount of $220,308.00 contingent upon certification from Jennifer Rodriguez
from Perkins and Will. The motion was
seconded by Josh Flowers and passed unanimously, 3-0. The requisition will then be signed by
Chairman Checco.
Mr. Verdi left at this time.
4. Project Updates for High School Renovation:
a. Morganti
Construction:
Mr. Schweitzer reported on the outstanding items from
the punch list:
o Boiler #1
Chairman Checco stated that there has been an ongoing dispute with Edgerton regarding
a faulty circuit and the boiler not operating from the beginning. Edgerton is claiming there is nothing wrong
with Boiler #1. Morganti will be
scheduling Edgerton to be onsite prior to the next MBC meeting. A representative from the MBC will attend that
meeting.
o Jockey Pump in the Fire Pump Building The pipe has been reexcavated and the bedding and
backfill are in the process of being done.
It is expected to be completed by Thursday, including paving and
patching. Mr. Schweitzer will confirm the
completion date. The line will be
retested.
o CRUV motors not operating Chuck Blaszka confirmed with R.J. Lucas regarding
the CRUVs and their operation. Mr. Lucas
has no issues with the CRUVs. Chairman
Checco will request this in writing from Messrs. Schatzle and Lucas.
o Locksets
The doors were ordered. Installation
will be completed prior to the next MBC meeting.
o Old Gym Overspray Morganti met with the painter onsite a few weeks
ago. They also met with Principal Luizzi and the Athletic Director and went
over the conditions. The painter will be
onsite on Friday to clean the north pads.
Chairman Checco asked whether Morganti had looked into
the leaks at the Nurses Office Unit and the Library Storage Unit. Mr. Schweitzer will follow-up on this.
b. JCJ Architecture: Mr. Kellogg was unable to attend the meeting.
Mr.
Schweitzer left at this time.
5. Correspondence: Memo from
Ralph Tedesco dated 8/12/10 regarding Trees.
6. Invoices:
Invoice # 310212801 from Control Network Communications
dated 7/4/10 in the amount of $2,385.00 for Cabling for the Senior Center will
be forwarded to Sam Khanthaphixay.
A motion was
made by Josh Flowers to approve Invoice #0083636 from Perkins & Will dated 7/8/10
in the amount of $2,740.59. The motion
was seconded by George Brown, Jr. and passed unanimously, 3-0.
7. Additional
Business: None.
8. Public
Comment: None.
9. Next
Meeting: The
next meeting is scheduled for September 21, 2010 at 7:00 P.M.
10. Adjournment: A motion was made by George Brown, Jr. to adjourn
the meeting at 7:45 P.M. The motion was
seconded by Josh Flowers and passed unanimously, 3-0.
Respectfully submitted,
Paul Checco
Chairman
Municipal Building Committee