EXPECTED
ROAD STATUS START DATE COMPLETION DATE
- Broadview Road 9/7/10 to be determined
·
Candlewood
Lake Road COMPLETED
- Elbow Hill (portions)
- Grays Bridge Road(Bridge
to Stony Hill Rd) COMPLETED
- Grays Bridge Road(Federal
Rd to bridge) ARRA Project COMPLETED
- Hidden Brook Drive COMPLETED
- High Meadow Road COMPLETED
- Horseshoe Road drainage work
started
- Johns Road COMPLETED
- Long Meadow Hill Road COMPLETED
- Merwin Brook Road COMPLETED
- North Mountain Road
- Obtuse Road South 9/9/10 to
be determined
- Old Turnpike Road #1 COMPLETED
- Pocono Road (#80 to 133)
- Prospect Court
- Prospect Drive
- Ridgeview Terrace
- Secor Road COMPLETED
- Silvermine Road COMPLETED
- Station Road
- Vale Road (to be determined)
- West Whisconier Road COMPLETED
- Woodview Road drainage work
started
PLEASE
NOTE: This list is subject to additions and/or deletions as conditions dictate.
Road
striping is done after hours